Project

UIH – Mechanical & Electrical Upgrades (949)

Scope

Air handling units s3, s5, s8, s9, s12 will be replaced in a sequence that allows the new units to be installed and fully operational with all associated ductwork modifications and  building automation controls prior to demolition of the existing air handling units. This will occur in a one-by-one installation/demolition process until all units have been upgraded. 

Project Summary

UIH – Mechanical & Electrical Upgrades (949)